Novouralsk projects
  Ozersk projects
  Snezhinsk projects
  Sarov projects
  Seversk projects
  Zheleznogorsk projects


"We will work" - Roman Galiev, the General Director of the Alucom factory,

Photogallery ...

Zheleznogorsk

Aluminum composite panels

Title

Purchase of the second production line of aluminum composite panels.

Objectives

The main project objective is to purchase the second production line of aluminum composite panels (ACP) of "Alukom" with the thickness of 3 mm. It will help to improve the quality of manufactured products and increase the sales volume. Thus, as a result of the project implementation "Alukom" will:
  • keep the market share it has among producers of ACP;
  • create additional 55 jobs, including at least 30 for former employees of MCK.

Summary

At present the company has one line for production of ACP with the thickness of 4-6 mm used for external decoration of buildings. The marketing research showed that in 2006 the consumption of ACP with the thickness of 4 mm would be 59,2%, 3 mm - 36,3% of the market. This proportion almost won't change till 2010. Therefore, in the project it is proposed to purchase, deliver, assemble and commission the second production line designed for production of high quality ACP with the thickness of 3 mm.

Also, in the framework of the project the heating systems in the production workshop will be reconstructed and the warmed warehouse.

It is planned to purchase auxiliary equipment which will make it possible to render additional services in ACP processing to customers:

  • Milling and engraving machine for cutting and milling of aluminum composite panels.
  • Machine for production of radial holders from aluminum composite panels.

Cost

Total cost of the project is £723,000. Contribution of the DTI amounts to £200,000.

Duration

18 months - from 31 March 2007 till 30 September 2008.

Beneficiary

"Rolling Plant "Alikom" Ltd., Zheleznogorsk

Project Consultant

Christophe Trontin, HTSPE Ltd.

Project Director

Greg Kaser, HTSPE Ltd.

Project Manager

Roman Galiev, "Rolling Plant "Alikom" Ltd.

Partners\Subcontractors

"DUK" Ltd. and "LPZ "SEGAL" Ltd.

[Print version] 