Novouralsk projects
  Ozersk projects
  Snezhinsk projects
  Sarov projects
  Seversk projects
  Zheleznogorsk projects


CNCP projects in the city of Seversk
TEPLOSTEN
Metal tungsten products
MDF Fascias
Wood Processing Facility
Ceramic products from nanopowders
Construction of a refinery
Energy saving centre
Fly-ash products
Training of personnel for NF3 production
Oxygen-18 isotope production
Modernisation of paper recycling enterprise
Zirconium diboride sputtering target

Seversk

Oxygen-18 isotope production

Title

Test bed creation for Oxygen-18 production.

Objectives

The aim of this project is to construct a test bed for Oxygen-18 isotope production technology adjustment.

Summary

Oxygen-18 is a stable isotope for which there is a rapidly increasing demand worldwide as a raw material for the production of Fluorine-18, which is widely used in Positron Emission Tomography (PET) to monitor brain function. The main customers for 18-O are hospitals and medical centres that have PET facilities or radio-pharmaceutical manufacturers who supply these facilities.

This project is to create a test bed laboratory for Oxygen-18 isotope production at SCK. This test bed will be used to prove the separating cascade production technology developed at SCK and will subsequently become a part of the full-scale production facility.

The DTI grant will support:

  • materials and equipment procurement;
  • laboratory construction;
  • software development;
  • maintenance schedule development;
  • staff retraining;
  • commissioning;
  • project management.

Cost

Total cost of the project is £180,008. The DTI is contributing of £150,008. The DTI funded £23,619 for preliminary research during fiscal year 2003/2004.

Duration

14 months - starting March 2005

Beneficiary

Siberian Chemical Kombinat (SCK), Seversk

Project Consultant

Jonathan Perks, AEA Technology Plc.

Project Director

Greg Kaser, HTSPE Ltd.

Project Manager

Alexander Krupin, SCK

Partners\Subcontractors

None

[Print version] 


Results of CNCP Steering Group Meeting
At the meeting on 19th February 2010 the CNCP Steering Group approved 29 projects...